Ninth & Rail · electrical · VP of Operations review
61% installed.78% of the labor spent.
General notes
Every floor, inked as installed
Graphite is installed work. Yellow is hours paid. Where the yellow passes the slab edge, the floor has used more than its whole budget.
Week 26as of Thu 12 Nov 2026
wk 14 · 6 to 9 released together
Installed work, from field quantity reports
Not yet installed
Hours paid, as a share of the floor's budget
Installed against spent
Cumulative hours, weeks 1 to 26 observed, 27 to 44 forecast by two methods.
Revision request
Three responses, measured against margin if nothing changes (method B). Assumptions are authored for this demonstration.
Instruments that change
Approvals for this revision
Watch, weeks 27 to 30
Replays of three authored outcomes. Nothing here is a prediction.